Architectural decoration T-slot pvc corners
$0.014-0.66 /Meter
Payment Type: | T/T,Paypal,Western Union,Alibaba |
Incoterm: | FOB,CIF,EXW,DDP,DDU |
Transportation: | Ocean,Land,Air,Express,Express |
Port: | Chongqing Guoyuan Port,Yiwu,Ningbo |
$0.014-0.66 /Meter
Payment Type: | T/T,Paypal,Western Union,Alibaba |
Incoterm: | FOB,CIF,EXW,DDP,DDU |
Transportation: | Ocean,Land,Air,Express,Express |
Port: | Chongqing Guoyuan Port,Yiwu,Ningbo |
Brand: QINGTAO
Selling Units | : | Meter |
Package Type | : | Plastic,cartons,pallet,or Customized |
Picture Example | : |
The file is encrypted. Please fill in the following information to continue accessing it
Points to note, construction procedures and techniques for installing and constructing Wall Corner PVC trunking
1. Spring line positioning: According to the water and electricity construction positioning and solidification drawings, determine the starting end to the end position of the line trough, calibrate the direction of the main line and branch line along the drawing, find the horizontal or vertical line, and use a laser level to locate the walls, ceilings, and beams along the line trough. Bounce or draw lines on , boards, columns, etc.; mark the position of fixed points or the positions of supports, hangers, and brackets.
2. Construction of fixed points or production and installation of supports, hangers, and brackets: Profile Pvc trunking is Anti Corrosion. When installed vertically against the wall, plastic expansion tubes or double-sided fixed points should be installed in a "Z" shape according to the marked fixed point positions. The rows should be fixed in parallel; when the wire trough is installed horizontally, the suspenders, brackets and brackets at both ends should be fixed first, and then the supports, hangers and brackets at both ends should be used as the basis to evenly set them using the cable pulling method.
3. Wire trough fixation: When installing PVC wire troughs, the trunk lines should be installed first and then the branch lines. The spacing between the fixing points of the trough or brackets and hangers should be even and standardized.
4. Wire trough installation: ① When the wire trough is laid horizontally, the support span is generally 1m. When the wire trough is laid vertically, the distance between fixed points should be ≤2m. The connection between the wire trough and accessories should be tight and smooth, with no gaps and no distortion. The trough cover After installation, it should be flat and without any warped legs.
②. Cable ties should be fixed in the cable trough and the cables should be bound.
Supply Capacity
Quantity(square meters) | 1-1000 | 1001-5000 | >5000 |
Lead Time(days) | 3 | 5 | To be negotiated |
Category | Fiberglass mesh | PVC Profile | Self-adhesive mesh |
Daily capacity | 100,000m² | 50,000m² | 30000m² |
Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.
Fill in more information so that we can get in touch with you faster
Privacy statement: Your privacy is very important to Us. Our company promises not to disclose your personal information to any external company with out your explicit permission.